How we work
Four steps from brief to first shipment, with the timeline and deliverables at each stage.
A first order usually reaches ex-factory in eight to twelve weeks. The difference between eight and twelve is almost never the sewing line — it is fabric, lab dips, trims, and the days a sample spends sitting on a desk.
So rather than quote you one number, here is the sequence, what moves it, and what we need from you to hold a date.
Four things, and the
first reply has numbers in it.
Missing one? Send what you have. We will ask for the rest in the first reply rather than the fourth.
A reference
A tech pack, a garment you have bought and want to match, or a flat sketch. Any format — a page of photographs beats a blank email. If it is a competitor's piece, send it: working backwards from a finished garment is most of what we do, and it is not a sensitive question.
Fabric direction
Composition and weight. "Soft and stretchy" costs you a week in back-and-forth. "Nylon-spandex, 220 gsm, matte" does not.
Quantity per colourway
This decides which fabrics are genuinely open to you, because mill minimums are set in metres, not in pieces. A 100-piece order on a stocked quality is straightforward; the same order on a made-to-order knit may not clear the mill's minimum at all.
Market and shelf date
Labelling and test requirements differ between the United States, the United Kingdom and the European Union, and a fixed launch date changes which of our answers are actually useful to you.
What happens,
in order.
Every stage below names what comes back to you, how long it takes, and what breaks it. The clock starts on our side only when the input is complete.
Share the brief
We read the brief against our development library before we price anything: 598 styles, with patterns, grades and fabric specifications already on file. If your style sits close to something we have already built, you start from an existing block and skip pattern development altogether. If it is genuinely new, we say so, and the sampling quote reflects the extra work instead of hiding it inside a number.
Back to you: within one business day — either a fabric shortlist with certification status and an indicative FOB, or a straight answer that the fabric direction will not work at your volume, and why.
Fabric and cost
The shortlist gives you, per fabric: composition, weight, the mill behind it, the certification it holds, and whether a transaction certificate will be issued at your order volume. That last line matters more than the certificate logo does. Eligibility is decided by the mill's minimum order, not by the certification on the label.
Then the costing. A BOM with fabric, trims, labour, packaging and margin as separate lines, and an FOB price per style. Quoted in US dollars, valid for 30 days.
We itemise it because it changes the conversation. If fabric is 60% of your cost, no amount of pressure on labour gets you to the price you want — the only real lever is the fabric, and you should be the one deciding to pull it.
Sampling and fit
15–20 working days, counted from an approved tech pack and fabric in hand. The clock does not start when you email.
Inside those days: pattern-making and grading across your size curve, a first fit sample cut and sewn, your fit session, the pattern correction, and a second sample or a full size set if the first one raised questions.
Two things break that window reliably. A style that needs a new block takes longer than one built on a block we already hold. And a tech pack with gaps — no graded spec, no construction detail, no artwork placement — guarantees a second round, because the first sample ends up answering questions nobody asked.
What you keep: the sample is charged at cost and the fee is credited against your bulk order, and the specification sheet is yours either way. If you take it to another factory, that is a legitimate outcome — we would rather you held a good spec than a lock-in.
Bulk and shipment
30–45 working days from sample approval and PO. At 100 pieces per style per colour, the sewing itself is a small part of that window.
What stretches it: colourway count splits dye batches and resequences cutting. Print, sublimation and bonded work add stations that run alongside sewing, not faster than it. Fabric still at the dye house pushes the start date by weeks rather than days.
Inspection runs in three passes — fabric checked on receipt, in-line inspection at the sewing stage, and a final AQL inspection before packing. Reports for fibre content, colourfastness and dimensional stability come from accredited third-party laboratories and travel with the goods.
Export documents cover the packing list, commercial invoice, fibre-content labels for your market, those test reports, and transaction certificates where the volume qualifies. We ship FOB Xiamen or Shenzhen, and quote FCA or DDP on request.
The days, and what
starts the clock.
Two rows carry no fixed number, and they are the two that decide your launch date. Fit approval sits with you. Fabric availability sits with the mill.
| Stage | Working days | The clock starts when |
|---|---|---|
| Quotation | 1 | Brief and reference received |
| Pattern-making and grading | Inside sampling | Tech pack approved |
| Sampling | 15–20 | Fabric in hand, specification locked |
| Fit review and approval | Your call | Sample in your hands |
| Bulk production | 30–45 | Sample approved, PO issued |
| Ex-factory | — | Production complete |
Where a week
goes missing.
None of the following happens on our floor. All of it moves the ship date.
- Your approval cycle
- A sample that sits three days on a desk adds three days. One consolidated set of fit comments, instead of three rounds of small ones, is worth more than any expedite we can offer.
- Lab dips
- A rejected dip costs roughly a week before the next one is on its way. Approve under a light box rather than on a phone screen — the colour you sign off on a display is not the colour you will receive.
- Fabric made to order
- A stocked quality books in days. A custom knit or a dye-to-order colour carries the mill's own lead time before sampling can begin.
- Trims developed late
- Custom woven labels, moulded zip pulls and heat-transfer logos have their own production windows, and they are usually longer than buyers expect.
- The calendar
- Chinese New Year closes the plant for two to three weeks, with a slow ramp either side. Golden Week and peak-season freight do the same thing at smaller scale.
- A late fabric swap
- Changing quality after the fit sample resets testing and, more often than not, resets the fit with it.
What it costs to start
No account minimum, no retainer, no annual volume commitment. A 100-piece order per style per colour is a real order here, not a trial we tolerate. Sampling is charged at cost and credited back against bulk.
You can stop after the sample and still keep the tech pack and the specification sheet. That is deliberate. A decision made with the garment in your hands is a better one than a decision made from a quotation.
And if we are not the right factory for the job, you will hear that in the first reply. It is cheaper for both of us than discovering it at the sample stage.
Start with the style
you want to make.
Send a reference, a fabric direction and a quantity. The first reply carries real options and an indicative price — or request a sample first if you would rather handle the fabric before committing.